Statement
I have been asked by my Right Honourable Friend, the Secretary of State to make this Written Ministerial Statement. This statement confirms that it has been necessary to extend the deadlines for decisions on the following two applications made under the Planning Act as indicated below to allow for further consideration of environmental matters:
- M25 Junction 28 Improvement project: for the proposed development by National Highways which would authorise the creation of a new two-lane loop road with hard shoulder, for traffic travelling from the M25 northbound carriageway onto the A12 eastbound carriageway towards Essex. The Secretary of State received the Examining Authority’s report on 16 September 2021 and the current deadline for a decision was 16 December 2021. The deadline is now extended to 16 May 2022.
- A1 Northumberland – Morpeth to Ellingham Improvements: the proposed development comprises the widening of approximately 20.6km stretch of the A1 between Morpeth to Ellingham with approximately 14.5km online widening and approximately 6.1km new offline highway. The Secretary of State received the Examining Authority’s report on 5 October 2021 and the current deadline for a decision was 5 January 2022. The deadline is now extended to 5 June 2022.
Under section 107(1) of the Planning Act 2008, the Secretary of State must make his decision within 3 months of receipt of the Examining Authority’s report unless exercising the power under section 107(3) to extend the deadline and make a Statement to the House of Parliament announcing the new deadline.
The Department will also endeavour to issue decisions ahead of the deadlines above wherever possible.
The decision to set new deadlines is without prejudice to the decisions on whether to give development consent for the above applications.