Skip to main content

Energy Infrastructure Planning Projects

Statement made on 2 September 2024

Statement UIN HLWS56

Statement

This Statement concerns an application for development consent made under the Planning Act 2008 by Ecotricity (Heck Fen) Limited for the construction and operation of a solar photovoltaic electricity generating station situated in Lincolnshire.

Under section 107(1) of the Planning Act 2008, the Secretary of State must make a decision on an application within three months of the receipt of the Examining Authority’s report unless exercising the power under section 107(3) of the Act to set a new deadline. Where a new deadline is set, the Secretary of State must make a Statement to Parliament to announce it.

The statutory deadline for the decision on the Heckington Fen Solar Park application was 9 August 2024.

Ecotricity (Heck Fen) Limited has requested that the Secretary of State extends the statutory deadline to allow time for further negotiations with landowners and to ensure the necessary permissions can be obtained. I have decided to allow a short extension and to set a new deadline of no later than 27 September 2024 for deciding this application for these reasons.

The decision to set the new deadline for this application is without prejudice to the decision on whether to grant or refuse development consent.

Linked statements

This statement has also been made in the House of Commons

Department for Energy Security and Net Zero
Energy Infrastructure Planning Projects
Michael Shanks
Minister for Energy
Labour, Rutherglen
Statement made 2 September 2024
HCWS52
Commons