Energy Infrastructure Planning Projects

Statement made on 15 April 2024

Statement UIN HLWS394

Statement

My Right Honourable Friend, the Secretary of State for Energy Security and Net Zero (Claire Coutinho MP) has today made the following statement:

This Statement concerns an application for development consent made under the Planning Act 2008 by Sunnica Energy Farm for the construction and operation of a solar photovoltaic electricity generating station, situated across West Suffolk and East Cambridgeshire.

Under section 107(1) of the Planning Act 2008, the Secretary of State must make a decision on an application within three months of the receipt of the Examining Authority’s report unless exercising the power under section 107(3) of the Act to set a new deadline. Where a new deadline is set, the Secretary of State must make a Statement to Parliament to announce it.

The current statutory deadline for the decision on the Sunnica Energy Farm application is 11 April 2024.

I have decided to set a new deadline of no later than 20 June 2024 for deciding this application.

The decision to set the new deadline for this application is without prejudice to the decision on whether to grant or refuse development consent.

Linked statements

This statement has also been made in the House of Commons

Department for Energy Security and Net Zero
Energy Infrastructure Planning Projects
Claire Coutinho
Secretary of State for Energy Security and Net Zero
Conservative, East Surrey
Statement made 15 April 2024
HCWS398
Commons