To ask His Majesty's Government whether construction of the first Fleet Solid Support ship has begun.

Answered on

3 July 2025

Successful delivery of the Fleet Solid Support (FSS) ship programme, which is currently in the design phase, remains a priority. The recent acquisition of Harland & Wolff (H&W) by Navantia UK, following the administration of H&W, has provided greater certainty to the delivery of the FSS programme and protects UK’s shipbuilding capability.

Construction has not yet begun, the design work is progressing well and production of the first FSS ship is expected to begin later in 2025, with all three vessels bolstering the Royal Fleet Auxiliary over the coming decade.