To ask the Secretary of State for Defence, what recent progress has been made on the E7 Wedgetail project.
Answered on
29 April 2024
The E-7 Wedgetail Programme submitted its Full Business Case as planned in March 2024 which will target an approval in 2024. The modification of the three E-7 Wedgetail aircraft continues at STS Aviation, Birmingham Airport, targeting an In-Service Date with the RAF in 2025.
Answered by
Ministry of Defence
Named day
Named day questions only occur in the House of Commons. The MP tabling the question specifies the date on which they should receive an answer. MPs may not table more than five named day questions on a single day.