Fleet Solid Support Ships: Construction

Question for Ministry of Defence

UIN 17805, tabled on 11 March 2024

To ask the Secretary of State for Defence, what recent discussions he has had with Team Resolute on its progress on meeting the target of including a minimum of 60% UK content in the construction of fleet solid support ships.

Answered on

20 May 2024

The Fleet Solid Support contract will create more than 1,200 UK shipyard jobs and around 800 jobs will be sustained in the UK supply chain. There is also substantial investment being made in the UK including around £100 million into UK shipyards, including £77 million of infrastructure at Harland & Wolff’s Belfast shipyard, the agreement will see a further £21 million invested in skills and technology transfer from Navantia UK. Whilst the majority of the work will take place in the UK, companies in the supply chain are still being engaged. There is also substantial investment being made in UK shipbuilding and ship design.

As prime contractor for the Fleet Solid Support ships Navantia UK is in the process of letting a number of contracts to UK companies, including those already let with BMT and Harland & Wolff. The value of the individual contracts is commercially sensitive information. It is expected that approximately 60% of the contract value will be with UK companies.

Named day
Named day questions only occur in the House of Commons. The MP tabling the question specifies the date on which they should receive an answer. MPs may not table more than five named day questions on a single day.