To ask His Majesty's Government, further to the Written Answer by Lord Davies of Gower on 14 February (HL2133), what are the minimum and expected timescales for the following stages of Ely Area Capacity Enhancement and upgrading of Haughley Junction: (1) the final business case, (2) the Ministerial decision to proceed to implementation, (3) the issuance of a Transport Work Act Order, (4) the commencement of works, and (5) the completion of works.
Answered on
28 February 2024
The recently announced Network North programme of investment included confirmation of government’s support for the Ely Area Capacity Enhancement (EACE) programme and the substantial benefits this will bring, including a doubling of passenger services on the Ely to Kings Lynn and Ipswich to Peterborough routes together with additional freight paths into the Port of Felixstowe.
Network Rail have developed the scheme to Outline Business Case stage; next steps will involve further investment case development and delivery planning.