To ask the Secretary of State for Energy Security and Net Zero, what her Department's policy is on the decommissioning of turbines and blades.
Answered on
30 November 2023
The decommissioning of all offshore wind turbines, including blades, is a legal obligation for the owners and their plans must be approved by the Secretary of State. Full removal of all offshore renewable energy installations is the default position and installations should be designed and constructed to facilitate that.
For onshore wind turbines and blades, when a local planning authority grants planning permission this will typically include conditions for decommissioning, such as returning a site to its previous state.
In both cases, all waste should be disposed of in accordance with the waste hierarchy.