To ask the Secretary of State for Defence, what is the parent project for each of the new build projects in the Devonport Royal Dockyard site plan; and what recent estimate he has made of the cost of each parent project.
Answered on
28 November 2023
The Devonport Submarine Infrastructure Programme will involve the investment of approximately £2.5 billion to provide new and refurbished facilities at HM Naval Base Devonport. The Department expects to gain beneficial use of the facilities currently under construction in 2024 (9, 14 and 15 Docks) and 2027 (10 Dock). The estimated costs for each project are commercially sensitive but they fall within the overall estimate of £2.5 billion.
Answered by
Ministry of Defence
Named day
Named day questions only occur in the House of Commons. The MP tabling the question specifies the date on which they should receive an answer. MPs may not table more than five named day questions on a single day.