To ask His Majesty's Government what amount they have spent so far on the proposed Holocaust Memorial in Victoria Tower Gardens; and what estimate they have made of the final cost of preparing the Holocaust Memorial Bill for introduction in Parliament.
Answered on
23 March 2023
Spend to date on the Holocaust Memorial programme is set out in the table below. No separate estimate has been made of the administrative cost of preparing the Holocaust Memorial Bill.
Figures in £m inc VAT Numbers may not sum due to rounding | Spend to Date | |
Client | ||
Staff | 3.6 | |
Contractors | 1.1 | |
Programme | 1.0 | |
Early programme expenditure | 0.6 | |
Total Client | 6.3 | |
Content Research and Development | 2.0 | |
Design | ||
Architect | 3.5 | |
Design engineer | 1.4 | |
Project and cost management | 1.2 | |
Technical support | 0.5 | |
Planning app and conditions | 0.5 | |
Peer Reviews and technical reports | 0.1 | |
Professional advice | 0.3 | |
Total Design | 7.4 | |
Exhibition Delivery | ||
Consultants | 0.2 | |
Designers | 0.2 | |
Total Exhibition Delivery | 0.4 | |
Construction | ||
Enabling works | 0.2 | |
Basement Box (pre-construction) | 0.1 | |
Total Construction | 0.3 | |
Planning Inquiry | 1.4 | |
Totals | 17.8 |