To ask the Secretary of State for Defence, what the (a) original cost expectations and (b) cost expectations as at 16 September 2022 were for the Spearcap 3 programme.
Answered on
27 September 2022
SPEAR Capability 3 was originally assessed at £1.554 billion and remains within the programme risk tolerance levels.
Answered by
Ministry of Defence