Guided Weapons: Procurement

Question for Ministry of Defence

UIN 51432, tabled on 20 September 2022

To ask the Secretary of State for Defence, what the (a) original cost expectations and (b) cost expectations as at 16 September 2022 were for the Spearcap 3 programme.

Answered on

27 September 2022

SPEAR Capability 3 was originally assessed at £1.554 billion and remains within the programme risk tolerance levels.