Skip to main content

Railway Stations: Greater Manchester

Question for Department for Transport

UIN HL240, tabled on 16 May 2022

To ask Her Majesty's Government what estimate they have made of the overall cost for the construction of the proposed Manchester HS2 (1) surface station, (2) rail-related buildings, (3) tunnels, (4) portals, and (5) track and signalling.

Answered on

27 May 2022

The High-Speed Rail (Crewe-Manchester) Bill Business Case and Overarching Estimate of Expense provide key cost estimates for the Phase 2b Western Leg.