To ask the Secretary of State for Business, Energy and Industrial Strategy, what assessment he has made of (a) the effect of rising sea levels on the proposals for Sizewell C in Suffolk and (b) the impact of the proposed site on (i) SSSI RSPB Nature Reserve and (ii) species in surrounding areas.

Answered on

25 October 2021

The examination of the application for development consent for the proposed Sizewell C nuclear power station closed on 14 October 2021 and the Examining Authority is now writing its report which will set out its conclusions and recommendations on the proposals.