Type 45 Destroyers: Repairs and Maintenance

Question for Ministry of Defence

UIN 51040, tabled on 17 September 2021

To ask the Secretary of State for Defence, what the planned timescales are for the completion of the Type 45 destroyer Power Improvement Package (PIP) upgrade.

Answered on

22 September 2021

HMS DAUNTLESS, the first of class ship to receive the Type 45 Power Improvement Project (PIP) conversion, is at the Cammell Laird shipyard in Birkenhead where equipment is being set to work following installation. The next phase of the programme will see HMS DAUNTLESS undertake a rigorous trials programme in harbour and subsequently at sea.

HMS DARING has been moved to the Cammell Laird shipyard in Birkenhead and will be the second Type 45 Destroyer to undergo her PIP conversion.

It is planned that all six Type 45 ships will have received the PIP conversion by the mid-2020s. The programme is dependent on the availability of ships to undertake the upgrade, balanced against the Royal Navy's standing and future operational commitments.