UIN 19488, tabled on 21 June 2021

To ask the Secretary of State for Defence, what his most recent estimate is of the (a) anticipated out-turn cost and (b) projected in-service date of each of the projects in the Atomic Weapons Establishment Site Development Context Plan.

Answered on

24 June 2021

The currently approved cost and in-service dates for AWE infrastructure projects, are as follows:

Project/Programme

Approved Cost

Approved In-service Date

MENSA

£1806 million

2023

PEGASUS

£634 million

Material Handling Store- 2025 Manufacture Capability - 2030

All outstanding infrastructure related projects at AWE remain in pre-approval stage and approved outturn cost and in-service dates are not available.