To ask Her Majesty's Government when they estimate the construction of Sizewell C nuclear power station will begin; and what funding model will be used for that construction.
Answered on
3 August 2020
It is for individual developers to consider milestones, such as estimates of when construction will commence. Any funding model would be agreed as part of a negotiation, should the Government enter into one.