To ask Her Majesty's Government, since the additional £300 million funding for Access for All was provided in April 2019, what progress has there been in each of the 73 stations ear-marked to benefit from the fund.

Answered on

2 July 2020

Network Rail have continued to successfully deliver the Access for All programme which is due to deliver a total of 110 accessible routes at stations between April 2019 and 2024. 11 of these projects have been completed and the remainder are at various stages of development and design. The Department and the Office of Rail and Roads are working closely with Network Rail to ensure the continued successful delivery of the programme and all projects remain on track to be completed by on schedule.