Skip to main content

High Speed 2 Railway Line: Buckinghamshire

Question for Department for Transport

UIN 220717, tabled on 13 February 2019

To ask the Secretary of State for Transport, what proportion of the the proposed High Speed Two tunnelling in Buckinghamshire will pass through ground which is clay with flints.

Answered on

18 February 2019

Approximately 200m of the tunnel will pass through a contiguous layer of clay with flints. This occurs for the final 200m of tunnelling near Great Missenden.

Named day
Named day questions only occur in the House of Commons. The MP tabling the question specifies the date on which they should receive an answer. MPs may not table more than five named day questions on a single day.