High Speed 2 Line

Question for Department for Transport

UIN 154563, tabled on 18 June 2018

To ask the Secretary of State for Transport, how much has been paid to each of the four joint ventures working on High Speed 2 Phase 1.

Answered on

21 June 2018

Approximately £173.2m has been spent to 18th June excluding VAT. This represents around 2.6% of total contract value.