Trident Submarines

Question for Ministry of Defence

UIN 136897, tabled on 20 April 2018

To ask the Secretary of State for Defence, from which budgets the cost of the Dreadnought programme’s trim and compensation system will be funded.

Answered on

27 April 2018

Costs of individual systems on Dreadnought are managed within the programme's overall £31 billion budget, which is funded by Defence. I am withholding details of the cost of this system as disclosure would, or would be likely to, prejudice commercial discussions and interests.