Skip to main content

F-35 Aircraft

Question for Ministry of Defence

UIN 132336, tabled on 13 March 2018

To ask the Secretary of State for Defence, what estimate he has made of the cost of upgrades to the F-35 in the next seven years.

Answered on

20 March 2018

The F-35 future development programme will see the aircraft upgraded from the baseline capability standard (Block 3F) to the first agreed set of new capabilities (Block 4). The F-35 Joint Program Office is currently determining the scope of this development programme and its associated cost. The UK's contribution will be around 4.5% of F-35 Program common upgrade costs, from which the UK gains 100% of the benefit. Approval for upgrade funding will be sought at the appropriate points in the programme.