To ask Her Majesty's Government when they expect the process of depositing waste material arising from the construction of the new Hinkley Point power station in the Cardiff Grounds to begin.

Answered on

26 March 2018

The dredge disposal will not commence until permission has been granted by the licencing authority. It is expected that work will begin summer 2018, once the permission has been granted.