To ask the Secretary of State for Business, Energy and Industrial Strategy, pursuant to the Answer of 12 September 2016 to Question 46335, and with reference to the Secretary of State Investor Agreement and Contract for Difference for Hinkley Point C signed by the Government on 29 September 2016, why he did not seek parliamentary approval for the liabilities incurred.

Answered on

19 October 2016

The Department laid a minute on 21 October 2015 outlining the liabilities that would be incurred by entering in to the contracts for Hinkley Point C. The minute can be found at:

http://qna.files.parliament.uk/qna-attachments/425357%5Coriginal%5C20151021%20Minute%20to%20Parliament%20HPC%20contingent%20liabilities.docx