Skip to main content

Biofuels: Renewable Heat Incentive Scheme

Question for Department for Business, Energy and Industrial Strategy

UIN 46162, tabled on 13 September 2016

To ask the Secretary of State for Business, Energy and Industrial Strategy, whether he will allow combined heat and power biomass plants pre-accredited under the Renewable Heat Incentive that are in-build but not yet in receipt of full accreditation to remain eligible under the rules of the scheme which prevailed at the time of the initial investment.

Answered on

18 October 2016

The Government has made changes to the Renewable Heat Incentive (RHI) Scheme Regulations 2011, and these amendments came into force on 1 August 2016.

The changes therefore apply to all new biomass-Combined Heat and Power plant with an accreditation date on or after 1 August 2016.

Answered by

Department for Business, Energy and Industrial Strategy