UIN 29383, tabled on 2 March 2016

To ask the Secretary of State for Transport, how many miles on what sections of the motorway network have been converted to Managed Motorways-All Lane Running (MM-ALR) status; and how many additional miles on which sections of the network Highways England plans to convert to MM-ALR by 2020.

Answered on

7 March 2016

The information requested is in the table below:

All Lane Running Scheme - Open for Traffic

Scheme Name

Scheme Length (miles)

Additional
lane miles

M25 J5-6/7

12.4

18.6

M25 J23-27

16.0

33.3

M1 J39-42

6.7

13.0

M6 J10a-13

9.6

19.0

All Lane Running Schemes - To be added by 2020

Scheme Name

Scheme Length (miles)

Additional
lane miles

M1 J28-31

18.9

38.5

M1 J32-35a

9.1

17.9

M62 J18-20

5.1

9.0

M3 J2-4a

13.4

26.8

M23 J8-10

10.4

20.8

M1 J24-25

5.2

10.4

M6 J16-19

18.2

36.4

M5 J4a-6

8.8

17.6

M60 J24-27 and J1-4

7.4

14.9

M6 J21a-26

9.9

19.8

M6 J2-4

11.8

23.6

M20 J3-5

5.6

11.2

Named day