To ask the Secretary of State for Transport, whether the GRIP 2 studies required for the Peninsula Rail Task Force's survey will be available in order for the survey to be completed in June 2016.
Answered on
3 February 2016
Department for Transport officials are working with Network Rail and the Peninsula Rail Task Force within the context of the changes that will come from Hendy re-profiling and the Bowe review to establish which further studies are required to inform the Peninsula Rail Task Force report of June 2016 and the funding that could be available to support this development work.
Answered by
Department for Transport