Skip to main content

Question for Ministry of Defence

UIN 20228, tabled on 15 December 2015

To ask the Secretary of State for Defence, with reference to the Answer of 2 July 2014, Official Report, column 676W on AWE, what his most recent estimate is of the (a) anticipated out-turn cost and (b) projected in-service date of each of the new build projects in the Atomic Weapons Establishment Site Development Context Plan.

Answered on

23 December 2015

The approved costs and in-service dates of the current new build projects at the Atomic Weapons Establishment, are shown below.


In-service dates are shown in bandings to avoid prejudice to national security and defence. No costs are attributed to projects detailed in Table 2 as these have yet to be formally approved.


Table 1 - Approved new-build projects



Ongoing projects

Function

In-Service Period

Approved cost £million

Warhead assembly/disassembly – Mensa

Manufacturing/production

2016-20

734

Uranium components – Pegasus

Manufacturing/production

2016-20

634


Table 2 – Planned projects not yet approved


Ongoing projects

Function

In-Service Period

Salts Processing - Octans

Testing/research

2020-25

Initiator system manufacture-Taurus

Manufacturing/production

2020-25

Large Scale formulations-Scorpius

Manufacturing/production

2025-30

Small Scale formulations-Cepheus

Manufacturing/production

2025-30

New Plutonium (Pu) Facility – not yet named

Manufacturing/production

2025-30

New depleted Uranium Facility

Manufacturing/production

2025-30

Assembly for Trials-Columba

Testing/research

2025-30

High Explosive Climatic Trials

Testing/research

2025-30

Non-Metallics & materials R&D-Libra

Testing/research

2025-30

Chemical processing-Astra

Manufacturing/production

2025-30