To ask the Secretary of State for Defence, with reference to the Answer of 19 June 2013, Official Report, column 718W, on AWE Aldermaston, what the final write-off costs were of the cancellation of Project Hydrus at the Atomic Weapons Establishment.
Answered on
17 December 2015
The final write off costs for the termination of Project Hydrus were £117.7 million. The hydrodynamics testing capability will now be delivered through the joint UK and France programme, Project Teutates. Components valued at £71 million which were constructed under Project Hydrus have subsequently been incorporated into Project Teutates.
Answered by
Ministry of Defence