Great Western Main Line: Electrification

Question for Department for Transport

UIN 13431, tabled on 26 October 2015

To ask the Secretary of State for Transport, when Network Rail first informed his Department of their estimate that electrification of the Great Western Main Line would cost more than £2 billion.

Answered on

29 October 2015

In June 2015, as part of the affordability review exercise, Network Rail informed Department that the latest estimated cost of Great Western electrification was around £2.4bn. This forecast costs remained uncertain and further work was required to validate this figure. The validation is being undertaken as part of the Hendy review and we await the publication in the Autumn.