Skip to main content

Midland Main Line

Question for Department for Transport

UIN 9751, tabled on 9 September 2015

To ask the Secretary of State for Transport, whether the four-tracking of the Midland Main Line from Bedford to Kettering and Corby is contingent upon the recommendations of the Hendy Review.

Answered on

14 September 2015

Kettering to Corby which is part 4 and part 2 tracking is currently in full implementation. Bedford to Kettering, in common with all rail projects, is subject to the recommendations of the Hendy Review which is due to report to the Secretary of State for Transport in the autumn.

Named day
Named day questions only occur in the House of Commons. The MP tabling the question specifies the date on which they should receive an answer. MPs may not table more than five named day questions on a single day.