To ask the Secretary of State for Transport, how many miles of the Great Western Main Line electrification project his Department plans will use (a) Series 1 overhead line equipment, (b) Series 2 overhead line equipment and (c) overhead line equipment built to other designs.

Answered on

6 July 2015

On the Great Western Network Rail have informed me that they plan to electrify 1100 single track kilometres with Series 1 Overhead Line Equipment. They have a further 160 single track kilometres which is still to be determined.