Skip to main content

High Speed 2 Line

Question for Department for Transport

UIN 228924, tabled on 24 March 2015

To ask the Secretary of State for Transport, what the total cost is of production of the Design Vision for High Speed 2.

Answered on

26 March 2015

The development and agreement of the design vision cost in total £77,000.

This included engaging with the design industry, carrying out a survey, running and full day seminar event, carrying out one-to-one interviews with leading designers, and carrying out consultation and development work with key staff followed by the production and print run of the design vision.