To ask the Secretary of State for Transport, what discussions he has had with Network Rail on the possibility of using CP6 funding to deliver the surface access improvements to Stansted Airport recommended in the Airports Commission Interim Report, published in December 2013.

Answered on

20 November 2014

The Airports Commission’s Interim Report recommended "work on developing proposals to improve the rail link between London and Stansted". To that end, we have challenged Network Rail to develop such proposals within the context of its Anglia Route Study, a draft of which is currently subject to public consultation. This integrated approach recognises that Stansted services share finite rail infrastructure with local, regional and long distance services.

The ultimate findings of the Anglia Route Study will influence the Government’s priorities for funding in Control Period 6.

Named day
Named day questions only occur in the House of Commons. The MP tabling the question specifies the date on which they should receive an answer. MPs may not table more than five named day questions on a single day.